There is a break in the rain today, so we were able to get the solar system frame installed.
Yesterday we brought the metal frame components to the site. With all the rain we’ve been having the first task was to remove the water and mud that had accumulated in all of the holes. It was a race with the weather as a severe storm moved in during the evening and will continue through tomorrow.
[nggallery id=24 template=caption]
Time to clean up and head over to Crane Alley for dinner and a few rounds of beer. Overall it was a successful day. Set all of the posts, installed all rails and most Unirac channel. Cement will be finished when a truck comes to pour the house foundation.